Traffic bulletin: Weeknight closures on M62 and A63 in East Yorkshire for upgrades

NATIONAL Highways is carrying out upgrades on the A63 between North Cave and Western Interchange (North Ferriby, Humber Bridge).   

National Highways Project Manager Jennifer Theaker said: 

 “This work will improve safety and reduce the need for future maintenance on this section of the route. The switch to LED lighting will also be better for the environment with less light pollution and reduced running costs.”  

National Highways is now carrying out the lighting replacements along with survey work overnight along sections of the route. This work is taking place ahead of improvements to the verges and central barrier, expected to begin in autumn.

To carry this out safely, closures will be in place between junction 37 of the M62 and the A63 at Western Interchange (North Ferriby, Humber Bridge) until Friday 18 August. The planned closures on the M62 are designed to minimise disruption to residents by directing traffic away from the area around junction 38 at North Cave. Junction 37 (Howden) is open as usual.  

The closures will be in place from 8pm until 6am each night during July, then between 9pm and 6am in August.    

Closures will be in place as follows:   

Date

 

25/07/2023 

Eastbound Full Closure 

26/07/2023 

Westbound Full Closure 

27/07/2023

Westbound Full Closure 

28/07/2023

Westbound Full Closure 

31/07/2023

Eastbound Full Closure 

01/08/2023

Eastbound Full Closure 

02/08/2023

Eastbound Full Closure 

03/08/2023

Eastbound Full Closure 

04/08/2023

Eastbound Full Closure 

07/08/2023

Eastbound Full Closure 

08/08/2023

Eastbound Full Closure 

09/08/2023

Eastbound Full Closure 

10/08/2023

Eastbound Full Closure 

11/08/2023

Eastbound Full Closure 

14/08/2023

Westbound Full Closure

15/08/2023

Eastbound Full Closure 

16/08/2023

Eastbound Full Closure 

17/08/2023

Eastbound Full Closure 

18/08/2023

Eastbound Full Closure 

When working in the central reservation area, there will be lane closures in the opposite direction for short distances, with reduced speed limits in place. 

Diversion  

A fully signed diversion is in place, taking into account motorway traffic including HGVs and height and weight restrictions in local villages and towns.

Westbound motorway traffic - leaving the A63 at Western Interchange (North Ferriby, Humber Bridge) onto the A614 re-joining the M62 at Howden.  

Westbound local traffic for Welton, Melton and South Cave (not suitable for HGVs) leaving the A63 at Western Interchange (North Ferriby, Humber Bridge) onto the A614, exiting onto Sancton Road at Market Weighton onto the A1034 and other local routes. 

Eastbound and Eastbound local traffic - will use the same routes as above but in reverse. 

People planning to travel in this area during the closures are advised to follow the signposted diversions and allow more time to reach their destinations. 

 

Andrew Jackson Solicitors LLP
Aa Global
Gold patron
Alan Boswell Insurance Brokers
ARUP
Connexin Live, Hull
CORY
Gold patron
Drax
East Riding of Yorkshire Council
Ellgia
Equinor
Gold patron
Hatfields Hull
KCOM
We are My
Orsted
OLG
Pattesons Glass Ltd
SPS Group
Streets Chartered Accountants
University of Hull
Wilkin Chapman LLP